Completed:
-Got prototype of shooter (motor and wheels) attached and functioning
-Dismantled Drive base, currently modifying in progress
-Pneumatic wheels tapped
*Jig for churros is in first teacher's cabinet on top shelf*
To do:
-Mount Shooter to Lexan
-Lexan scoop (cut part got burnt off)
-Finish modifying drive base to accommodate pneumatic wheels
-Mount Pneumatic wheels to above mentioned drive base
-Mount Lexan Side guides
Gear box mounting plate for rear-wheel drive (preferably milled)
Also, if anyone would like to come out on Saturday from 9-2 for the UOIT Lego League with a robot and other parts ONLY TEAMS A-C, F
NOTICE: TEAM MEMBERS ON E (1-5) SHOULD BE ON STANDBY TO COME TO MORNING SHIFT INSTEAD OF SCHEDULED DUE TO LACK OF SUPERVISION
-Got prototype of shooter (motor and wheels) attached and functioning
-Dismantled Drive base, currently modifying in progress
-Pneumatic wheels tapped
*Jig for churros is in first teacher's cabinet on top shelf*
To do:
-Mount Shooter to Lexan
-Lexan scoop (cut part got burnt off)
-Finish modifying drive base to accommodate pneumatic wheels
-Mount Pneumatic wheels to above mentioned drive base
-Mount Lexan Side guides
Gear box mounting plate for rear-wheel drive (preferably milled)
Also, if anyone would like to come out on Saturday from 9-2 for the UOIT Lego League with a robot and other parts ONLY TEAMS A-C, F
NOTICE: TEAM MEMBERS ON E (1-5) SHOULD BE ON STANDBY TO COME TO MORNING SHIFT INSTEAD OF SCHEDULED DUE TO LACK OF SUPERVISION
Last edited by max yan on Fri Jan 15, 2016 7:24 pm; edited 1 time in total
Max Yan- Posts : 29
Join date : 2014-10-16
Age : 23
Re: January 14 Team B Build Shift (6-9)
Drivebase will now be chain driven. Also pneumatic wheels have all been removed from fribee robot and tappes 1/4 20. But we can not use the belt drive hubs they will not sink with wheels. So moving forward no more work on shooter or in take prior to a drive base being completed.
chefjohn- Admin
- Posts : 158
Join date : 2012-06-19
Re: January 14 Team B Build Shift (6-9)
Saturday shifts will go ahead as previously planned. Team D 9-1 and team E 1-5.
Kelly McCarthy- Posts : 7
Join date : 2012-02-05
Similar topics
» Team A Build Shift January 24 (9-1)
» Team A Build Shift January 17 (1-5)
» Team E Build Shift January 19 (6-9)
» Team D Build Shift Januray 19th 3-6
» 9-1 shift on January 16th log
» Team A Build Shift January 17 (1-5)
» Team E Build Shift January 19 (6-9)
» Team D Build Shift Januray 19th 3-6
» 9-1 shift on January 16th log
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum
|
|