Team C 21/01/2016 6-9
Page 1 of 1
Team C 21/01/2016 6-9
Done
• Talons zip tied on
• Motor connected to power distributor board
• Fixed/organized all the wiring
• Support for shooter replaced with c channel
To be done
• Add hinges on the plate for electrical board
• Hook up electrical on computer
• Continue wiring shooter
• Create worm drive on single motor
• Adjust front roller wheel to be inside perimeter of robot
**REFER ALL WIRING DONE TO THE DIAGRAMS CONTAINED WITHIN BLUE 2016 KICKOFF PACKAGE**
• Talons zip tied on
• Motor connected to power distributor board
• Fixed/organized all the wiring
• Support for shooter replaced with c channel
To be done
• Add hinges on the plate for electrical board
• Hook up electrical on computer
• Continue wiring shooter
• Create worm drive on single motor
• Adjust front roller wheel to be inside perimeter of robot
**REFER ALL WIRING DONE TO THE DIAGRAMS CONTAINED WITHIN BLUE 2016 KICKOFF PACKAGE**
Muhammad Aayan- Posts : 10
Join date : 2013-10-03
Age : 25
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum
|
|