Team A feb 18 6-9
Page 1 of 1
Team A feb 18 6-9
Done
To Do
- Soldered connectors on second drive base for the drive motors and talons
- Worked on roller pickup
- Finished some bumper pieces(no one was sure what they were exactly for)
To Do
- Roller needs to be finished - Contact Will
- Connect drive motor wires to PDB
- Bumpers need to be finished as well
- Cut angle iron for second drivebase