Team F Friday Feb 5 (3-7)
Page 1 of 1
Team F Friday Feb 5 (3-7)
Done
- Mounted window motor but also replaced the metal plate with a lexan plate
-Churros for drive base B were threaded and mounted
-Got bearings permanently mounted for shooter B
To Do
-Connect window motor to the speed controller
-Get wires from speed controllers long enough to reach the areas where shooter A would be mounted for the motors
-Assemble drive base B (we were missing some important screws so they were ordered today)
- Mounted window motor but also replaced the metal plate with a lexan plate
-Churros for drive base B were threaded and mounted
-Got bearings permanently mounted for shooter B
To Do
-Connect window motor to the speed controller
-Get wires from speed controllers long enough to reach the areas where shooter A would be mounted for the motors
-Assemble drive base B (we were missing some important screws so they were ordered today)
Ayman Shaikh- Posts : 18
Join date : 2013-09-26
Age : 24
Similar topics
» Team E Friday 29
» Team D Friday January 22
» Team D Feb 14 9-1
» Team C 01/28/16 3-6
» Team A feb 18 6-9
» Team D Friday January 22
» Team D Feb 14 9-1
» Team C 01/28/16 3-6
» Team A feb 18 6-9
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum
|
|